HuaTianLogo

Power detection technology / Power detection

Detection Technology

How to phase distribution transformers on site?

time:2025/5/16   source:Wuhan UHV  reading:433 time

Checking the phase of distribution transformers is a routine task in the power system. The specific operation steps are as follows:

Transformers intended for parallel operation must undergo phase determination testing before formal parallel power transmission. The method of phase determination test is to connect two transformers with parallel conditions, with both primary sides connected to the same power supply, and measure whether the secondary phase is the same on the low-voltage side. The steps for phase determination are:

(1) Measure the voltage of two transformers separately to see if they are the same.         

(2) Measure the voltage difference between terminals with the same name. When the voltage difference on each terminal with the same name is almost zero, it can be operated in parallel.       The FRD high-voltage core phase generator produced by Wuhan UHV power can complete the above functions and is an indispensable tool for high-voltage electricians.


Copyright description: all articles, pictures, video and other materials on this site belong to wuhan huatian power automation co., LTD. For use, please contact us; Permission to reprint articles, pictures, video and other materials please quote "from: huatian power".
  

Test items for power transformers  | 2025/5/16 | reading444time Misconceptions in the operation of a megohmmeter  | 2025/5/16 | reading391time return