Precautions for primary current injection tester
A current injection tester is an essential equipment for current debugging in various industries. Applied to power plants, substations, electrical equipment manufacturing plants, research laboratories and other units. High current generators have the characteristics of small size, light weight, good performance, and easy use and maintenance. A current injection tester is an essential equipment for current debugging in various industries. Applied to power plants, substations, electrical equipment manufacturing plants, research laboratories and other units. It has the characteristics of small size, light weight, good performance, and easy use and maintenance. Cable connection.
Precautions for use and maintenance of primary current injection tester
1. When not in use for a long time, use a 500V megohmmeter to check the insulation resistance of the main circuit to ground before use.
2. The input voltage should be based on the voltage values on the nameplate (-220V, -380V), with a difference of ± 10% and a frequency of 50Hz.
3. Current switches are not allowed to operate with load.
4. When operating, the handwheel should be rotated at a constant speed and slowly to avoid damaging the regulator.
5. Full load working time shall not exceed 5 minutes, continuous working time shall be less than 2.5 minutes, but the working cycle shall be greater than 10 minutes.
6. The booster housing has a grounding terminal. Good grounding should be ensured during use.