Used for AC voltage test of common electrical insulation tools
Note:
Regarding product purchase, technical maintenance and other services, welcome to send email:
The automatic electric power safety equipment testing platform is developed on the basis of the requirements of the State Power Company on issuing the notice of "Preventive Test Procedures for Electric Power Safety Equipment" (trial) (Guodianfa [2002]777) and the State Grid Company's electric power safety working procedures (substation part). The product indicators are in line with the requirements of the national standard. Intelligent insulation voltage resistance test can be carried out on insulation shoes, insulation gloves and other safety appliances according to the requirements of the "Preventive Test Procedures for Electrical Safety Appliances". The resistance test period of insulation shoes and insulation gloves is half a year, and no breakdown is allowed during the test. At the same time, the leakage current of insulation shoes and insulation gloves is not greater than the limit value. The products are suitable for all power related industries.
Product nickname£ºInsulation boot (glove) withstand voltage, insulated boots gloves withstand voltage tester, auxiliary insulation tool test device, insulated boots insulated gloves test device, insulated protective device insulation test device, insulated shoes insulated gloves test machine, insulation Boot insulation gloves testing machine
Insulating boot test | Voltage | 15kV |
Leakage current | ¡Ü6mA | |
time | 1min | |
Resolution | 0.1kV¡¢0.1mA | |
Precision | Voltage¡À£¨2%£«3d£©Current¡À£¨2%£«3d£© | |
Insulating glove test | Voltage | high pressure£º8kV Low pressure£º2.5kV |
Leaking Current | high pressure¡Ü9mA Low pressure¡Ü2.5mA | |
time | 1min | |
Resolution | 0.1kV¡¢0.1mA | |
Precision | Voltage¡À£¨2%£«3d£©Current¡À£¨2%£«3d£© | |
Insulating rubber pad test | Voltage | high pressure£º15kV Low pressure£º3.5kV |
Leaking Current | No breakdown | |
time | 1min | |
Resolution | 0.1kV¡¢0.1mA | |
Precision | Voltage¡À£¨2%£«3d£©Current¡À£¨2%£«3d£© | |
Custom test | Voltage | 1-30kV |
Leaking Current | 1-20mA | |
time | 1-10min | |
Resolution | 0.1kV¡¢0.1mA | |
Precision | Voltage¡À£¨2%£«3d£©Current¡À£¨2%£«3d£© | |
Working power supply | AC220V 50Hz | |
Output Voltage | 0-30kV | |
Capacity | 3kVA | |
test numbers | 6 pcs each time | |
Ambient temperature | £10¡æ ¡« £«50¡æ | |
Operating box volume | 35*22*37cm | |
Operating box quality | 12kg | |
Test vehicle volume | 75*90*102cm | |
Test vehicle quality | 60kg |
1. The appearance of the product is subject to the actual product. The Technical Parameters and model numbers are subject to change without notice. If there is misappropriation or copying, legal liability will be pursued.
2. For more information about Wuhan UHV, please enter product center . Service email£ºqiao@hvtest.cc
1, the instrument can carry out the test of 8 insulating boots or insulating gloves at the same time, and measure the leakage current of each test product.
2, insulation shoes test using a small steel ball placed inside the dry test method, get rid of the traditional filling shoes to do the test, after the test is not easy to dry.
3, high and low pressure separation, leakage current using anti-interference wireless transmission technology to transmit back to the control box, great protection of personal safety.
4, each test has a breaking mechanism, when any one of the breakdown or exceed the set leakage current value, the test will automatically out of the test, does not affect other test.
5, the instrument uses 7 inch TFT touch large screen LCD Chinese character display, display large amount of information, a screen at the same time display test voltage, 8 high voltage leakage current, perpetual calendar, timing time and other parameters as well as Chinese prompt content.
6, the use of DC motor control voltage regulator boost process, fully automatic voltage test. After the start of the test, the automatic closing of the instrument to the national standard requirements of the speed of automatic voltage boost, reach the predetermined voltage start time, and maintain the test voltage, time to, automatic voltage drop, to zero after automatic power off, prompt the end of the test, at the same time display the leakage current of each test, and automatically save the test results.
7, insulation boots test with a special stainless steel grounding tray, insulation gloves test with a special stainless steel container, easy to operate.
8, the test transformer ratio can be set freely, but also can be matched with the customer's existing transformer.
9, with overcurrent protection function.
Enterprise products in strict accordance with international and national standards and rules of industry production, through the national, provincial and municipal electric power research institute and electric power authorities detection, measuring center, fully passed the ISO9001 international quality management system certification, the licence for manufacturing measuring instruments of the People's Republic of China, GB/T19001-2016 quality management system requirements, GB/T24001-2016 environmental management system requirements, GB/T45001-2020 occupational health and safety management system requirements.